Four bedrooms over two storeys, a 32 m² pool and generous terraces, furnished and ready to let, on a flat lot in town. The estimate comes to US$945,000 to US$1,469,000, likely US$1,180,000, with design, permits, VAT and a reserve.
The estimator did not load. Try again in a moment.
(Estimate)
- Likely
- Construction
- Fees, permits, VAT
- All in, a m² built
(From a budget)
What a budget builds here, with the choices above. Pick one to use it.
(Construction, by part)
(Design, permits and taxes)
(What the estimate covers)
Included
- Construction, with the builder's profit and administration
- Studies, design, drawings, cost estimate and technical direction, at the CFIA minimum
- Municipal permit, CFIA charges and the INS work insurance
- VAT at 13%
- A reserve of 5 to 10%
- The pool, terraces, solar, landscaping and furniture you pick, and condominium design reviews
Not included
- The land unless you tick it, and its legal and transfer costs
- The water letter, a long water line or a well
- A power line to the lot
- Access roads and long driveways
- A septic tank or a treatment plant
- Condominium review fees and deposits
Rates updated 7 October 2026, at ₡457.80 to the dollar. They price houses designed by an architect; a typical local house (Hacienda types VC01 to VC04) runs about US$640 to 1,050 a m².
(Schedule)
DesignPermitsConstructionDry season
(To keep in mind)
(The project)
- A house
- 320 m² over 2 storeys
- High finish
- Flat lot
- A 32 m² pool
- 80 m² of terraces and decks
- Solar panels
- Landscaping
- Furniture, ready to rent
Rentals earn in the dry season, from December to April, so the schedule matters as much as the budget: a villa that misses one opening of the dry season starts earning a year later. Furniture ready to rent is in the number; the land is not.
(What moves the number)
- A standard finish−US$311,000
- A luxury finish+US$467,000
- Without the pool−US$51,000
- On a steep lot+US$238,000
- 20% less area−US$212,000
- Without furniture−US$88,000
The likely figure, with one thing changed and the rest as above.
(Questions)
How much does it cost to build a rental villa in Tamarindo, Costa Rica?
About US$945,000 to US$1,469,000, likely US$1,180,000, with design, permits, VAT and a reserve: construction at about US$2,156 a m², and about US$3,688 a m² with everything in.
How long does it take to build the house?
About 5 months of design, 3 of permits and 15 of works, which start once the permits are in and run straight through the rains. From the first meeting to moving in, plan on 2 years or a little more.
What makes it cost more or less?
A standard finish: −US$311,000; A luxury finish: +US$467,000; Without the pool: −US$51,000; On a steep lot: +US$238,000; 20% less area: −US$212,000; Without furniture: −US$88,000.
Does the estimate include the land?
No. Titled lots of 300 to 5,000 m² listed in Tamarindo ask a median of US$418 a m²; tick "The land" in the estimator above to add it.